OUTLINE SCOPES of WORK
- Electrical (EC) – Repair all existing electrical systems, lights, outlets, switches. Replace (2) main panels.
- Mechanical (MC) - (2) new gas boilers and controls, new baseboard on 1st floor, repair remaining existing baseboard.
- Plumbing (PC) – Check all fixtures and drains, make all operational, install new drain(s) in Kitchen sinks.
- General Construction (GC) – Repair or replace sheetrock, doors, frames, hardware, patching, paint, carpet, refinishing, millwork, toilet partitions, window hardware and glazing, locks, and roofing.
- Roofing (by GC) – Replace entire roof.
- Window Glazing (by GC) – Reglaze broken or missing window glass.
- Fire Alarm /Security System (FA) – by Owner. Install fully addressable system, plus 24/7 monitoring.
- Kitchen Equipment (KE) – by Owner. Provide appliances adequate to serve 50 people per meal. Refrigerator, freezer, prep table(s), dishwasher.
- Chimney Inspection (CI) – by Owner. Perform chimney inspection with written report.
- Kitchen Fire Extinguisher System (ANSUL) – by Owner. Service existing system.
- Boiler (BO) – Replace Boiler, and fix internal heating system.
- Laundry Room (LR) – Turn existing room near bar into a Laundry facility buy adding hookups for 4 dryers and 3 washers.
- Study Room (SR) – Add electric & CAT5 wiring to basement study room area
ESTIMATED CONSTRUCTION SCHEDULE
Note: Exact Construction Schedule Varies by Trade
Early Start: December 1, 2007
Late Start: February 1, 2007
Early Finish: February 28, 2007
Late Finish: April 30, 2007
Art Harvey
Chairman of the Board
Gamma Epsilon of TKE, Inc.
|